Why is the road construction in the east ring road of Qingyang City suspended?

No more funds.

The project was originally planned to be constructed according to the "loan to build road, repay loan with toll" model. Because the original tunnel of the project is 4127 meters long and has a long construction period, it is a full-line controlled project. The Qingyang Municipal Government has accelerated the To promote project construction, it was decided to implement the controlled engineering construction of the double-hole tunnel in Zhenyuan boundary in advance, with a view to synchronous construction of the entire line. During the project advancement process, due to major adjustments in national investment and financing policies, the originally determined project capital lost its source, resulting in the inability to finance construction across the board.