I. Process of Agricultural Land Conversion (approved by Pingdingshan Municipal Government)

1. Project establishment and feasibility study. Provided by the land unit. (The time is determined by the land unit)

2. Land measurement. The Municipal Bureau of Natural Resources and Planning and the land-using unit will conduct on-site survey and confirmation with the people of villages and towns (streets) and village groups, and prepare a land survey and demarcation report (3 days, with a relatively long land area).

3. hearing. Led by the land unit, the Municipal Bureau of Natural Resources and Planning will hold a hearing in conjunction with townships (streets) and village groups. (1 day)

4. The Planning Section of the Municipal Bureau of Natural Resources and Planning applies for the annual construction land planning index to the Usage Control Section of Pingdingshan Municipal Bureau of Natural Resources and Planning, and at the same time files it with the Provincial Department of Natural Resources. (Time to be determined)

5. Group papers. The Farming and Protection Division of the Municipal Bureau of Natural Resources and Planning has drawn up the "one book and two plans" (construction land reporting instruction, agricultural land conversion plan and supplementary cultivated land plan), as well as the municipal government's request for instructions and review opinions on agricultural conversion. Attached is the invoice of cultivated land reclamation fee and the confirmation sheet of cultivated land occupation and compensation balance. (The cultivated land reclamation fee shall be paid by the finance department or the land user to the non-tax account of the Finance Bureau) (3 days)

6. The Municipal Natural Resources and Planning Bureau organized papers and submitted them to the municipal government for issuance of instructions. (Time to be determined)

7. Pingdingshan City Bureau uses the control section to accept after the preliminary examination, and organizes the on-site reconnaissance of relevant departments such as the use control section, the tillage and maintenance section, the spatial planning section and the law enforcement team. (1 day).

8. Pingdingshan City Bureau of Natural Resources and Planning came together (the joint examination department is the field investigation department). (Time to be determined)

9 Pingdingshan Municipal Bureau of Pingdingshan Municipal Government for approval (three departments of the municipal government). (Time to be determined)

10. After the approval of Pingdingshan Municipal Government, it shall be filed with the Provincial Department of Natural Resources. (2 days)

Process: project establishment → land survey → hearing → composing papers → reporting to Pingdingshan → site survey → joint review by Pingdingshan Municipal Bureau → approval by Pingdingshan Municipal Government.

Two, the city batch, township batch land acquisition process (the provincial government for approval)

1. Project establishment and feasibility study. Provided by the land unit. (The time is determined by the land unit)

2. The municipal government issued a notice to start land expropriation. The announcement time is not less than 5 working days.

3. Land measurement. Led by the land-using unit, the Municipal Bureau of Natural Resources and Planning will conduct on-site survey in conjunction with towns (streets) and village groups, and prepare a land survey and demarcation report. (3 days)

4. The municipal government issued an announcement on the compensation scheme for land acquisition and resettlement. The announcement time is not less than 30 days. Most people have objections to the resettlement compensation scheme, and the Municipal Bureau of Natural Resources and Planning organizes a hearing.

5. Sign the land acquisition compensation and resettlement agreement. Villages and towns (streets) and landless rural collective economic organizations and landless farmers signed resettlement compensation agreements respectively. (The time is determined by the township and street)

6. The Municipal Bureau of Natural Resources and Planning (Planning Section) applies to Pingdingshan Municipal Bureau (Use Control Section) for the annual plan index of construction land. (Time to be determined)

7. Group papers. The Land Division of the Municipal Bureau of Natural Resources and Planning has drawn up "one book and three plans" (report instruction, land acquisition plan, agricultural land conversion plan and supplementary cultivated land plan), as well as the municipal government's land acquisition request documents and review opinions, letters and visits evaluation, and attached social security fees, cultivated land reclamation fee bills, cultivated land occupation and compensation balance hook confirmation sheet and related maps. (The social security fee shall be paid by the Finance Bureau to the financial special account of the People's Social Security Bureau, and the cultivated land reclamation fee shall be paid by the financial department or the land user to the non-tax account of the Finance Bureau) (7 days)

8 municipal government issued land requisition documents. (Time to be determined)

9 submitted to Pingdingshan City Natural Resources and Planning Bureau for acceptance. (1 day)

10. Pingdingshan Municipal Bureau organized on-site reconnaissance (Space Planning Section, Use Control Section, Law Enforcement Team, Farming and Conservation Section, Natural Resources Investigation Section). (Time to be determined)

1 1. The joint hearing of Pingdingshan Municipal Bureau (Space Planning Section, Use Control Section, Law Enforcement Team, Farming and Conservation Section, Natural Resources Investigation Section, Letters and Calls Section) was reported to Pingdingshan Municipal Government. (Time to be determined)

12. Pingdingshan municipal government issued instructions and submitted them to the Provincial Department of Natural Resources (Usage Control Office) for review. (Time to be determined)

13. After the joint examination of the Provincial Department of Natural Resources (Usage Control Department, Farming and Conservation Department, Natural Resources Investigation Department, Space Planning Bureau and Law Enforcement Bureau) is passed, the new fee will be paid to the Provincial Department of Finance, and then reported to the provincial government (five departments) for approval. (The paid use fee for new construction land shall be paid by the financial department). (Time to be determined)

14. After the approval of the provincial government, it shall be filed with the Use Control Department of the Provincial Department of Natural Resources, and the Pingdingshan Municipal Government shall forward the approval documents of the provincial government. (Time to be determined)

15. The municipal government issued a land requisition announcement. (2 days)

16. The township (street) is responsible for the compensation in place (the compensation includes the area price, young crops fee and the compensation fee for the ground attachments, which is raised by the Finance Bureau). (The time is determined by towns and streets)

Process: project establishment → launching land acquisition announcement → land measurement → publishing land acquisition plan announcement → signing agreement → composing papers → reporting to Pingdingshan → site survey → reporting to the Provincial Department of Natural Resources → reporting to the provincial government for approval → publishing land acquisition announcement → land acquisition compensation.

Three, the transfer of land use rights (listing) procedures

1. Project establishment and feasibility study. Provided by the land unit. (The time is determined by the land unit)

2. Land measurement. Land units take the lead, and the Land Reserve Center of the Municipal Natural Resources and Planning Bureau organizes planning departments, cadastral departments and other departments to conduct on-site surveys in conjunction with towns (streets) and village groups, and prepare land survey and demarcation reports. Belonging to the state-owned stock of land, it is necessary to report to the municipal government for approval to recover the land. (Land compensation is needed to recover state-owned land, and the funds shall be allocated by the financial department). (3 days)

3. Formulate planning indicators. The land and space planning section of the Municipal Natural Resources and Planning Bureau draws up various planning indicators for land transfer according to the control regulations. (2 days)

4. Land price evaluation. The Municipal Land Reserve Center entrusts a third-party evaluation agency to conduct on-site reconnaissance and issue a land price evaluation report (which needs to be filed with the Ministry of Natural Resources). (5 days)

5. Land price consultation. Members of the Municipal Land Management Committee will conduct on-the-spot reconnaissance of the specific land parcel, and hold a land price meeting after the consent of the main leaders. (Time to be determined)

6. Report to the municipal government for approval. The Reserve Center of the Municipal Bureau of Natural Resources and Planning drew up a land transfer plan and submitted it to the Legal Affairs Department of the municipal government for review before issuing the approval document. (Time to be determined)

7. issue a transfer announcement. City land reserve center to develop land transfer notice, in the Ministry of natural resources and Henan land market trading online announcement. (30 days)

8. Sign the transaction confirmation. After the transaction is successful, the municipal land reserve center will sign a transaction confirmation with the bidder and publicize it on the website of the Ministry of Natural Resources. (5 days)

9. Sign a transfer contract. The land transfer contract drawn up by the utilization department of the Municipal Bureau of Natural Resources and Planning was publicized on the websites of the Ministry of Natural Resources and the Provincial Department of Natural Resources. The publicity signed the transfer contract with the bidder through the Municipal Bureau of Natural Resources and Planning, and all the land transfer fees were paid within 60 days. (10 days)

10. Apply for land use planning permit. The Land and Space Planning Section of the Municipal Natural Resources and Planning Bureau handles the land use planning permit according to the land transfer contract and other relevant materials. (2 days)

1 1. Issue immovable property certificate. The municipal real estate registration center shall register the land according to the approval document of land transfer, the confirmation of transaction, the land transfer contract, the invoice of land transfer fee, the deed tax payment, the certificate of farmland occupation tax, and the survey results of ownership (provided by the land user). (1 day) (cultivated land occupation tax is allocated by the financial department to the land reserve center or paid by the land user to the tax bureau, and deed tax is paid by the land user to the tax bureau).

Process: project establishment → land measurement → formulation of planning indicators → land price evaluation → land price negotiation → reporting for examination and approval → issuing transfer announcement → signing transfer contract → handling land use planning permit → issuing immovable property certificate.

Four, the land use right allocation procedures

1. Project establishment and feasibility study. Provided by the land unit. (The time is determined by the land unit)

2. Land measurement. Led by the land-using unit, the Municipal Bureau of Natural Resources and Planning organized the Planning Department, Cadastral Department and other departments to conduct on-site survey in conjunction with towns (streets) and village groups, and prepare the land survey and demarcation report. (3 days)

3. Go through the EIA procedures. The land-using unit shall, jointly with the environmental protection department, go through the EIA procedures. (The time is determined by the land unit)

4. Apply for land use planning permit. The land use unit shall provide relevant information to apply for a land use planning permit to the Land and Space Planning Section of the Municipal Natural Resources and Planning Bureau. (2 days)

5. Group examination. The Utilization Section of the Municipal Bureau of Natural Resources and Planning, together with the Farming and Conservation Section, the Land Use Section, the Planning Section, the Cadastral Section and the Legal Affairs Section, will draw up a land allocation and land supply plan.

6. Report to the municipal government for approval. The utilization section of the Municipal Natural Resources and Planning Bureau will submit the proposed land allocation plan to the Legislative Affairs Office of the municipal government for review and approval. (Time to be determined)

7. Issue the land allocation decision. The utilization section of the Municipal Natural Resources and Planning Bureau publicized the land supply plan approved by the municipal government on the websites of the Ministry of Natural Resources and the Provincial Department of Natural Resources, and publicized the land allocation decision issued by the Municipal Natural Resources and Planning Bureau. (10 days)

8. apply for a real estate certificate. The municipal real estate registration center shall register the land according to the approval document of the municipal government, the land allocation decision, the certificate of paying farmland occupation tax and the survey results of ownership (provided by the land user). (The farmland occupation tax is allocated by the finance department to the land reserve center or paid by the land user to the tax bureau) (1 day)

Process: project establishment → land measurement → project establishment → environmental assessment → handling land use planning permit → municipal government approval → issuing allocation decision → handling real estate certificate.