Construction organization design of Jiangxi 25-story clothing building project?

What is the specific content of the construction organization design of the Jiangxi 25-story Garment Building project? Zhongda Consulting will answer it for you below.

1.1 Basis for preparation

1) Bidding documents for ×× Garment Building Project;

2) "×× Garment Building Project" designed by ×× Architectural Design Institute Construction drawings of buildings, structures, water and electricity";

3) Our company's IS09002 quality manual and procedure control documents;

4) Our company's many years of experience in housing construction and construction:< /p>

5) Characteristics of the project, construction site survey data;

6) National, industry, and Nanchang City norms and procedures regarding construction and construction quality, construction safety, civilized construction, etc. , rules, standards and other documents;

7) The company's construction management capabilities and technical equipment levels;

1.2 Technical standards adopted

1) "Building Foundation" "Basic Engineering Construction Acceptance Standard" (GB50202-2002)

2) "Masonry Engineering Construction Quality Acceptance Standard" (GB50203-2002)

3) "Concrete Structure Engineering Construction and Acceptance Specifications" (GB50204-2002)

4) "Welding Regulations and Provisions for Building Steel Structures" (JGJ8-91)

5) "Technical Regulations for Concrete Pumping Construction" (JOJ /Tl0-95)

6) "Steel Bar Welding and Acceptance Regulations" (JGJl8-96)

7) "Construction Quality Acceptance Regulations for Building Decoration and Renovation Projects" (GB50201-2001)

8) "Design Regulations for Ordinary Concrete Mix Proportion" (JOJ55-2000)

9) "Design Regulations for Mixture Proportion of Masonry Mortar" (JGJ98-2000)

< p>10) "Unified Standard for Quality Inspection and Assessment of Construction and Installation Projects" (GB50300-2001)

11) "Specifications for Archiving and Arrangement of Construction Project Documents" (GB/T50328-2001)

12) "Safety Technical Specifications for Steel Pipe Scaffolding in Construction" (JGJl28-2000)

13) "Construction Project Management Specifications" (GB/T50326-2001)

1.3 Project Overview< /p>

1.3.1 Project location and basic situation

The ×× Garment Building Project is located on the south side of ×× Road, Nanchang City. It is about 134m long from east to west and 81m wide from north to south. It covers an area of ??about 12,000 square meters and the total construction area is about 120,000 square meters.

This project has basically completed demolition, temporary roads, temporary drainage facilities, temporary walls and other projects. The three connections and one leveling of the construction site have been basically completed.

1.3.2 Structural Overview

The engineering structure is a cast-in-place steel frame-shear structure with 25 floors above ground and 1 floor underground. The seismic fortification is 7 degrees. The seismic grade of the frame is Level 2. , this project will be fortified against earthquakes as a Class I building.

1.3.3 Project Characteristics

1) The project construction period is tight and it is a cast-in-place structure, so it is necessary to formulate an economical and reasonable construction plan, strengthen the management of turnover materials, and ensure the construction The construction schedule, quality and safety achieved the expected goals.

2) The construction site is adjacent to the commercial wholesale market, and people come and go frequently, so special safety protection measures must be formulated.

3) This project is located in Hongcheng Market, on the south side of Hongcheng Road, and during the construction process, the podium building will be opened for business, so civilized construction on site is very important. Therefore, during construction, It is necessary to ensure that the site is clean and tidy, every process must be completed, and all materials must be used, and civilized construction must be carried out.