Implementation plan for the reconstruction of shantytowns in the old city

2017 Implementation Plan 1 for the Reconstruction of Shantytowns in the Old City

In order to speed up the pace of the transformation of shantytowns in the old city, comprehensively enhance the urban appearance of the old city, and effectively improve the shantytowns in the old city The living environment of residents is based on the requirements of the district government's "Implementation Plan for the Renovation of Old City Shantytowns" and combined with the actual situation of our office, this plan is specially formulated.

1. Guiding Ideology

Our overall guiding ideology in shanty town reconstruction is: adhere to the principles of unified planning, rational layout, comprehensive development, and supporting construction, and follow the guidance of the government , market operation, overall planning, and phased implementation? Implement the high-standard, planned, and step-by-step transformation of old city shantytowns to further improve the living environment of urban residents, increase the capacity of economic development carriers, enhance the city's comprehensive service functions, and comprehensively promote The construction of harmonious community.

2. Targets and tasks

In 2017, our office will start the renovation of two shantytowns, Wenhua Garden (old courtyards 122# and 124#, Lishan Road) and Dongshefang. Among them, the old courtyards at 122# and 124# on Lishan Road cover an area of ??52 acres, with a total existing building area of ??43,000 square meters and 660 households; the East Shefang Shantytown covers an area of ??55 acres, with a total existing building area of ??37,000 square meters. , the number of households is 360.

Through transformation, it is ensured that shantytowns are transformed into new communities with complete facilities, supporting services, beautiful environment, orderly management, civilization and health, and where people can live and work in peace and contentment.

3. Implementation steps

The renovation of shantytowns in the old city is carried out in four stages.

1. Investigation stage. Led by the Urban Management Section of the office and assisted by the community committees, a special team was formed to conduct a wide-net survey of the units and households in the two shantytowns to ensure that the data was accurate and detailed, laying the foundation for future demolition and investment promotion work. . Assist the District Construction Committee to estimate land maturation costs and register them.

Time: April 2017? May 2017

2. Publicity and investment stage. Led by the economic committee of the office, in accordance with the principles of "overall planning, complete renovation, bundled bidding, market operation, and social win-win", the investment projects are packaged and planned, promoted to the outside world, publicize preferential policies for shanty town renovation, and proactively and develop Communicate with business partners, follow up closely, achieve results, promote project implementation, and complete project signing.

Time: June 2017 to December 2017

3. Demolition mobilization stage. Led by the urban management section of the office, with the assistance of community neighborhood committees, special personnel will be organized to go deep into the shantytowns to do a good job in explaining the policies and publicity and mobilization of the demolished people, doing a good job in stabilizing the demolished residents, and assisting the district demolition office in solving targeted problems. The actual difficulties faced by the relocated residents shall be addressed to ensure the smooth progress of the demolition and resettlement work.

Time: June 2017 to December 2008

4. Responsibility implementation stage. The office designates a dedicated person to dynamically supervise the shantytown reconstruction process, implement various policies for shantytown reconstruction one by one according to the progress of shantytown reconstruction, and actively ensure the smooth progress of the project.

Time: December 2017? December 2009

IV. Organizational Leadership

1. Establish a leadership organization. The office has established a leading group for shanty town reconstruction work with the secretary of the Party Working Committee as the team leader, the office director and the director in charge as deputy team leaders, and the heads of relevant departments as members, and is fully responsible for the organizational leadership of shanty town reconstruction in the jurisdiction.

2. Clarify work responsibilities. The office economic committee will take the lead and be responsible for investment promotion, project release, project negotiation and external investment promotion. Led by the Urban Management Section of the office, it is mainly responsible for the investigation of shantytowns, formulating renovation project plans, project review and declaration; publicity and education on project demolition, mobilizing the active support and active participation of the demolished people to ensure the stable and smooth progress of the demolition work; organization and coordination, Supervise management and daily work.

The member units of the leading group must cooperate with each other according to their respective functions, strictly follow relevant regulations, and actively cooperate to complete the renovation of shantytowns.

3. Strengthen supervision and management. The office implements shanty town reconstruction in accordance with the principles of "openness, fairness, impartiality and open operation". In particular, policies, standards and procedures for shanty town reconstruction must be publicly announced, and important links such as demolition, construction, and resettlement must be publicly announced and consciously accept public supervision. Strictly implement the work responsibility system, assign work tasks to specific leading cadres and staff, combine supervision and inspection with annual assessment, and enhance the sense of responsibility. Establish a dynamic management system for the supervision and inspection of shantytown reconstruction work. The progress of shantytown reconstruction will be scheduled every Monday, inspected once a month, and inspected every quarter. Problems will be discovered in a timely manner, dealt with, and supervised for implementation. 2017 Implementation Plan 2 for the Renovation of Old City Shantytowns

In order to conscientiously implement the "Opinions of the State Council on Further Relevant Work on the Renovation of Urban Shantytowns and Urban and Rural Dilapidated Buildings and the Construction of Supporting Infrastructure" (State Development Council [2015 ]37) and the "Nanning City 2017 Shantytown Renovation Work Plan", implement the shantytown transformation as an important measure to expand effective investment, promote new urbanization and protect people's livelihood, further accelerate the shantytown transformation work in our city, and effectively To improve the living environment, enhance urban functions and quality, and do a good job in the shanty town reconstruction work in our city in 2017, this work plan is specially formulated.

1. Guiding ideology

Conscientiously implement the spirit of the Central Urban Work Conference, the National and District-wide Housing and Urban-Rural Construction Work Conference, and the spirit of the 14th Plenary Session of the 11th Municipal Party Committee, combined with the spirit of the autonomous region The party committee and the government have put forward the work requirements of Nanning City to renovate and renovate the old city of Nanning City in celebration of the 60th anniversary of the founding of the autonomous region, and the work ideas to improve the quality of living, and coordinate and promote the renovation of shantytowns in our city.

2. Work Objectives

According to the "Nanning City 2017 Shanty Town Renovation Project Work Objectives and Responsibility Letter" signed between the Nanning Municipal People's Government and our district, our district's 2017 responsibility goals and tasks It will serve 2,600 households and strive to meet the requirements for the project to start full construction by the end of 2017.

3. Organizational structure

The Xingning District shanty town reconstruction work leading group (hereinafter referred to as the "leading group") was established to be fully responsible for the organization and command within the jurisdiction of Xingning District , coordinate and advance work.

IV. Division of responsibilities

(1) Each town (sub-district office): is the main unit responsible for the comprehensive improvement of old residential areas and is responsible for the comprehensive improvement of old residential areas within its jurisdiction. The project work organization carries out full-process tracking, coordination, mass ideological mobilization and service work; does a good job in mediation, petitions, stability maintenance and handling of remaining issues, etc.; does a good job in the shanty town reconstruction project as the main expropriation unit.

(2) Urban Housing and Urban-Rural Development Bureau: Responsible for guiding, coordinating, organizing, cooperating and supervising the main units responsible for shanty town reconstruction projects and the main units responsible for comprehensive rectification to carry out their work in accordance with the law.

(3) Urban Land Acquisition and Demolition Office: coordinate the timely allocation of compensation fees for expropriation and demolition of comprehensive renovation projects and shantytown reconstruction projects; guide the responsible units responsible for expropriation and demolition to complete the house expropriation work for each shanty town reconstruction project; Do a good job in the work related to the shanty town reconstruction project of this department as the main unit responsible for expropriation and demolition.

(4) Urban Finance Bureau: Responsible for the implementation of comprehensive renovation funds for old residential areas, special funds for shanty town reconstruction, and CDB loan funds, and make overall arrangements for funds.

(5) Urban Supervision Bureau: Responsible for supervising and inspecting the rectification work carried out by towns (streets) and communities in accordance with the law, as well as the legal use of various funds and fees; investigating and punishing disciplinary violations in work according to law and discipline.

(6) Other relevant departments in the urban area: Cooperate with the work related to shanty town reconstruction projects and comprehensive renovation projects according to their respective functions and in accordance with the law.

5. Main work contents and requirements

(1) Complete the shanty town reconstruction tasks in different time periods according to time nodes

The start time of the shanty town reconstruction project in 2017 The node requirements are: achieve 50% construction start by the end of August; achieve 90% construction start by the end of October; achieve 100% construction start by the end of November.

(2) Accelerate the process of expropriation and demolition work and promote monetized resettlement work

Accelerate the progress of project expropriation and ensure that the project is implemented and started as soon as possible; according to the relevant policies of the municipal government, Actively promote resettlement methods such as organized group purchasing, centralized purchasing, and self-service shopping, and guide the rehabilitated households to choose monetary resettlement.

(3) Vigorously carry out comprehensive renovation work in old residential areas

In accordance with the spirit of the Central City Work Conference and the work deployment of the Autonomous Region Housing and Urban-Rural Development Department, organize personnel to conduct a thorough investigation and conduct a thorough investigation of some residential areas. Old residential areas with incomplete supporting facilities, poor living environment, and safety hazards in the houses that are difficult to demolish and rebuild should be comprehensively renovated and renovated through urban coordinated implementation, social forces contracting construction and construction, and residents' participation.

(4) Complete monthly reports and information data

Before the 25th of each month, report the progress of the 2017 Shanty Town Renovation Project to the Municipal Urban and Rural Development Committee on time, and fill in the autonomous region residence report Data related to the construction department information system.

(5) Actively apply for and implement subsidy funds

Carefully study relevant documents, interpret policies, closely contact the Autonomous Region Construction Department, Autonomous Region Finance Department, and Municipal Finance Bureau, and actively provide assistance to shantytowns. Renovation projects apply for national and autonomous region financial subsidy funds, make good use of them, and broaden funding channels.

(6) Increase efforts to attract investment and do a good job in recruiting project mature people

According to Nanning City's "Implementation Plan for Publicly Soliciting Land Mature Persons to Raise Social Funds for Pilot Projects to Advance Old City Renovation" According to the relevant provisions in the shantytown renovation project, organize the recruitment of mature people for shantytown renovation projects, mobilize social forces to participate in the renovation work, and solve the funds required for demolition and demolition of shantytown renovation projects.

(7) Accelerate the use of CDB Shantou Renovation Project Loans

Strengthen coordination and communication with CDB Guangxi Branch, seek support from CDB Guangxi Branch, and adopt projects and loan types Adjustments and other methods will be adopted to speed up the use of loan funds that have been implemented for projects.

(8) Pay close attention to the project quality and safety, and promote the completion of the project

Carefully pay attention to the project quality and safety of newly started projects, and improve the quality and safety of newly started projects in 2014 and 2015. The completed projects are included in monthly reports for statistics and tracking.

VI. Work Measures

(1) Strengthen organizational leadership and clarify work responsibilities

Attach great importance to the transformation of shantytowns and further improve the organizational structure of shantytown transformation. Formulate a work implementation plan, refine the target tasks, break down and assign tasks to towns, streets, and communities to coordinate and guide each shed renovation project, as well as related house expropriation, land acquisition and demolition, construction progress, quality and safety There are clear responsible leaders and personnel responsible for all aspects such as petitions, petitions and stability maintenance.

(2) Accelerate the pre-commencement procedures to achieve the start-up target

Accelerate the pre-project work, all relevant functional departments will cooperate closely, handle urgent matters in an urgent manner, and speed up the start of the project The handling of preliminary procedures ensures that the start-up target is achieved in accordance with the time requirements and creates favorable conditions for project financing.

(3) Establish a working system and accelerate the progress of the work

Establish systems for shanty town reconstruction work meetings, information submission and progress notification. Develop a work plan for shed renovation and inversion, and report work progress and problems on a monthly basis.

(4) Strengthen supervision and assessment to ensure work implementation

First, the leadership group regularly organizes supervision of the promotion of shanty town projects, verifies the progress of each project, and promptly Discover and coordinate to solve existing problems, and supervise responsible units, towns, streets and communities that have failed to implement the work to improve their sense of responsibility in carrying out their work.

The second is that the leadership group organizes performance appraisals, and rewards are given to those who have done outstanding work. In addition to deducting points according to the performance appraisal indicators, those who fail to complete the tasks will be interviewed by members of the leadership group, and those who fail to complete the tasks will be interviewed. Units and individuals that engage in favoritism, malpractice, or neglect their duties during the shantytown reform work will be held accountable.

(5) Vigorously promote the expropriation and demolition work to promote housing reform

First, we must further implement the main responsibilities and vigorously promote the demolition work so that the housing reform project can be implemented and invested. can be implemented; secondly, it is necessary to increase the publicity of expropriation, demolition, compensation and resettlement policies and regulations, so that relevant policies can be deeply rooted in the hearts of the people and accepted by the people, collect, answer and process the opinions and suggestions of the people in a timely manner, and strive for the people's understanding of the shed reform work and support.

(6) Cooperate with the audit

Cooperate with the audit department to follow up and audit the shantytown reconstruction project. Strengthen coordination and cooperation with the audit department, promptly rectify and provide feedback on problems discovered during the audit, summarize experience, draw inferences from one instance, improve policies and measures, strengthen supervision, and prevent recurrence of problems.