My company wants to build a staff dormitory, may I ask what formalities need to go and to which departments?
Enterprise self-build approval procedures:

One, for land acquisition procedures (that is, for construction land use permits) to provide:

1. project approval;

2. general drawing (design institute);

3. environmental assessment approval;

4. planning red line control map (the second side of the road must be the Office of the Planning to the site to delineate the red line).

Two, before the start of the relevant procedures (i.e., for the construction project planning permit) to provide:

1. General plan, effect map (must be reviewed and approved by the town);

2. Geological exploration report;

-1-

3, each house single architectural design drawings;

4, fire audit opinion, land use approval;

5, must use new wall materials;

6, by the urban construction center to put the line checking line before the start of construction;

7, to pay the infrastructure support fee of 5 yuan / square meter.

Four, after the start of construction for:

1. land use certificate;

2. construction management quality supervision, construction permits;

3. certificate of acceptance of completion of the project;

4. real estate license.