The implementation of the construction schedule should be combined with the specific conditions of the project construction and based on the milestones determined by the controlled construction schedule.
The main functions of implementing the construction progress plan are as follows:
(1) Determine the specific arrangement of construction work;
(2) Determine (or calculate) the labor demand (type of work and corresponding quantity) for one month or ten days;
(3) Determine (or calculate) the demand for construction machinery (name and quantity of machinery) for one month or ten days;
(4) Determine (or calculate) the demand for building materials (including finished products, semi-finished products and auxiliary materials, etc.). ) One month or ten days (name and quantity of building materials);
(5) Determine (or calculate) the monthly or ten-day fund demand, etc.