Current location - Loan Platform Complete Network - Bank loan - How to calculate the construction cost of highway site laboratory
How to calculate the construction cost of highway site laboratory
Project description and calculation formula

Direct engineering costs (i.e. labor, materials and machinery costs)

Prepare the annual budget price according to the project location.

Other engineering costs

(a) the comprehensive rate of other engineering costs or the sum of all kinds of engineering labor and machinery costs * the comprehensive rate of other engineering costs

net cost

) ten (

All kinds of engineering labor cost × comprehensive cost rate +(3) × comprehensive enterprise management fee.

24

overhead expenses

Five idle profits under comprehensive interest rate

[(3)+(4)- cost] × utilization rate

Tax one (three)+(four)+(five)] × comprehensive tax rate

Than the cost of construction and installation.

(3)+(4)+(5)+(6)

Expenses for purchasing equipment, tools and appliances (including (purchase quantity of equipment, tools and appliances× unit price+transportation and miscellaneous expenses )× (1+purchased spare parts) office and living furniture purchase expenses.

Purchase and deposit rate) is calculated according to relevant regulations.

Other expenses such as engineering construction, compensation for land acquisition and demolition.

Calculate the management fee of the health establishment unit according to the relevant regulations.

(7) × rate

Engineering quality supervision fee

(7) × rate

Engineering quota determination fee

(7) × rate

Design document review fee

(7) × rate

The inspection fee for military (handover) acceptance test shall be calculated according to relevant regulations.

(7) × rate

Research and test fees

Prepare according to the approved plan.

Pre-project cost

Calculated according to relevant regulations

Special assessment fee

Calculated according to relevant regulations

Construction organization relocation fee

Calculate the power supply subsidy according to the actual situation

Calculated according to relevant regulations

Joint debugging fee

(7) × rate

Training fee for production personnel

Calculated according to relevant regulations

Adjustment tax on investment direction of fixed assets

Calculate the loan interest during the construction period according to relevant regulations.

Interest is calculated according to the actual loan amount and interest rate.

reserve fund

Including price difference reserve and basic reserve.

If the price reserve is calculated according to the prescribed formula.

Basic reserve funds

[(7)+(ハ)+(9)-Adjustment fixed assets investment direction tax-loan interest during construction] × interest rate

Contract coefficient of construction drawing budget in reserve fund

(3)+(4)] × Total construction cost calculated at the rate.

(7)+(ハ)+(9)+(+)