What are the procedures for wind power generation projects?
Legal analysis: summary of procedures required in each stage of wind power project.

2018-11-2917:11:03 new energy investment and financing circle Author: Tourongjun

In the second half of the year, influenced by the photovoltaic "53 1 New Deal", more and more development companies joined the wind power development army. Recently, many friends asked Tou Rongjun what procedures are needed for wind power development projects. Today, Tourongjun will sort it out for you.

(Source: New Energy Investment and Financing Circle Author: Investment and Financing Jun)

I. Pre-declaration documents

1, wind power project development agreement

2. Wind resource assessment report

3, to carry out the preliminary work of the letter

4. Land Pre-examination (Bureau of Land and Resources)

5, forest right certificate (Forestry Bureau)

6. Advance Access Letter (Power Supply Bureau)

7. Environmental Impact Report (EPA)

8. Preliminary site selection opinions (Ministry of Housing and Urban-Rural Development)

9. Opinions on site selection of cultural relics (Cultural Relics Bureau)

10, military reply (Armed Forces Department)

1 1. Opinions on overburden (Land and Resources Bureau)

12. Incorporate the annual construction index and/or subsidy index certification documents.

Second, the project approval documents

1, project feasibility study report and its technical review opinions 2. Pre-examination opinions on project land use.

3, environmental impact assessment reply

4, safety pre-evaluation report for the record letter

5. Opinions on grid-connected operation of wind farms or coordination of grid-connected projects.

6, financial institutions agreed to give the project financing loan documents

7. Wind resource assessment report

8. Project application report

9, overlying mineral data evaluation report and overlying mineral opinions

10, review comments on energy conservation assessment

1 1. Suggestions on planning and site selection of construction office

12, geological disaster risk assessment report for the record (if any)

13, social stability risk assessment reply document

14, soil and water conservation recovery

15. approve the approval document.

Three. Commencement document

1, access system approval document and electricity price guarantee letter

2. Compensation documents for land requisition/occupation and vegetation restoration (if any)

3, agricultural land conversion approval procedures (if any)

4, the state-owned construction land allocation decision (if any)

5. Land use right transfer contract (if any)

6 lease of collective land, the need to provide collective land ownership certificates and village collective resolutions of more than two thirds of the villagers/villagers' representatives.

7. Approval document for occupation of forest land/grassland (if any) and forest cutting license (if any)

8, construction land planning permit

9, the construction project planning permit

10, construction permit for construction project

1 1, preliminary design review document.

Four, power generation business documents

1, power generation project access system design scheme and review comments

2. Power station grid-connected protocol/grid-connected dispatching protocol

3, grid-connected production documents

4. On-grid tariff reply

5, power grid safety assessment report

6, purchase and sale of electricity contract

7. Power business license (power generation).

Legal basis: Article 12 of the Interim Measures for the Administration of Wind Power Development and Construction. Before carrying out the preliminary work, the wind power project development enterprise shall submit an application to the energy department of the government at or above the provincial level to carry out the preliminary work of wind power project development. According to the division of project approval authority, the application for preliminary work of 50,000 kilowatts and above project development is accepted by the provincial government energy department and reported to the the State Council energy department for approval. The enterprise can carry out the feasibility study of the project only after obtaining the approval issued by the competent department to carry out the preliminary work. Interim Measures for the Administration of Preliminary Work of Wind Farm Projects Article 12 The feasibility study of wind farm projects is conducted on the basis of the pre-feasibility study of wind farm projects, which is the basis for the government to approve the construction of wind farm projects. The feasibility study of the wind farm project shall be completed by the enterprise that has obtained the project development right in accordance with the national regulations and requirements on wind power construction and management.